Implementation Plan: Platform Operations
- Status: Implementation plan ready for stakeholder review — implementation not authorized
- Capability: Platform operations
- Task list target:
tasks/todo.md - Last updated: 2026-08-20
Confirmed implementation direction
Build a Qlockify-style, single-Ubuntu-server platform for zarinpal.amiirkhl.ir. A trusted Docker-group deployment user manually pulls the latest main in the deployment, backend, and frontend repositories; records all three commit hashes; builds locally with Docker Compose; migrates; verifies health; and records the release. Rollback restores the previous hashes and rebuilds.
There is no CI/CD pipeline, runner, private image registry, or automated cross-repository trigger. PostgreSQL backup/restore adapts Qlockify's existing scripts with minimal project changes and excludes environment/secrets. Prometheus/Grafana are a required second phase after MVP readiness and before AI work.
No task below is authorized merely because it appears here.
Dependency graph
resolve concrete server/runtime inputs + authorize build
|
+--> safe config + manual release-record contract
| |
| +--> Compose data/app services
| | |
| | +--> migrate/import/admin separation
| | +--> manual deploy/rollback
| |
| +--> Nginx/Certbot routing and TLS
|
+--> Qlockify backup adaptation --> guarded restore --> rehearsal
|
+--> first-server bootstrap --> MVP acceptance
|
v
Prometheus/Grafana phase
|
v
AI may begin
Architecture decisions
- Preserve ADR 0001's three independent repositories and ignored nested service checkouts.
- Follow accepted ADR 0002: latest
main, record three hashes, build manually on the server, store active/previous release records. - Follow accepted ADR 0003 and frontend commit
64f5ac2: ordinary frontend context only for font/license. - Use PostgreSQL 18 and Redis 7 Alpine with explicit supported tags.
- Keep PostgreSQL authoritative and backed up. Redis remains excluded from disaster-recovery backup.
- Separate API, worker, migration, one-time CSV import, and administrative processes.
- Keep Asynq pinned to pre-1.0
v0.26.0. - Use automatic Let's Encrypt/Certbot TLS.
- Treat structured logs/health/manual checks as MVP; add Prometheus/Grafana after MVP and before AI.
Phase 0: resolve implementation inputs and authorize the build
- Treat the approved Platform Operations spec and ADRs 0001–0003 as the implementation baseline.
- Obtain the production IP/DNS state, repository URLs, actual protected environment values, ParsPack endpoint/bucket/prefix/credentials, and named operator/secret-escrow contacts.
- Obtain the backend command contract for API, worker, migration, import, admin, liveness, readiness, and Redis-loss recovery.
- Obtain the frontend build/static health contract.
- Obtain explicit authorization before creating deployment implementation artifacts.
Checkpoint: no implementation file exists before explicit build authorization and the inputs needed by its slice are resolved.
Phase 1: configuration and Compose foundation
- Add safe tracked configuration examples and validate protected external secret paths.
- Define non-secret active/previous release records containing the three SHAs and health/migration evidence.
- Implement isolated Compose networks, PostgreSQL/Redis volumes/health/resources, backend/worker/frontend services, and one-off migration/import/admin profiles.
- Add focused validation for ports, startup ordering, font build presence, and forbidden tracked/runtime artifacts.
Checkpoint: clean local/server validation proves only Nginx will publish ports and normal startup cannot trigger import/admin.
Phase 2: Nginx, TLS, and lifecycle
- Adapt Qlockify Nginx/Certbot structure for
zarinpal.amiirkhl.ir. - Implement canonical redirect/default-host rejection, API/frontend separation, exact SSE route, security headers, caching, and health behavior.
- Implement manual deploy/release/rollback from Qlockify's script structure without unconditional destructive Git reset.
- Exercise failed pull/build/migration/readiness/font/worker conditions while preserving the active release.
Checkpoint: manual deployment records the three SHAs, passes TLS/health/SSE checks, and a prior-hash rebuild rollback completes within 15 minutes.
Phase 3: backup, restore, and first-server acceptance
- Minimally adapt Qlockify backup/upload/restore/S3-restore scripts for ZarinPal paths/services/credentials.
- Remove Qlockify environment-file backup/restore; include PostgreSQL archive plus non-secret manifest/checksums only.
- Add exact destination and production confirmation guards.
- Bootstrap the server with
first-start.sh: migrate, import/reconcile the pinned archive, then activate public services; perform separate credential setup, encrypted remote backup, and a clean restore rehearsal within two hours.
Checkpoint: every MVP acceptance criterion passes through manual health/log/disk/certificate/queue/backup checks.
Phase 4: required observability before AI
- Add Prometheus, Grafana, and minimum private exporters/instrumentation.
- Add service/release, worker/SSE, PostgreSQL/Redis, host/container, backup/restore, and TLS dashboards.
- Add bounded labels, retention, symptom-based alerts, runbook links, and tested notification delivery.
- Validate the observability acceptance gate before any AI implementation starts.
Checkpoint: an induced failure is detected, correlated to the three-hash release, diagnosed from telemetry, and alerts reach the responsible operator.
Risks and mitigations
| Risk | Impact | Mitigation |
|---|---|---|
| Manual deploy selects inconsistent source | Broken stack | One deployment lock, latest three main checkouts recorded before build, one release record |
| Dirty checkout is destroyed | Lost operator/user work | Fail on dirty/divergent state; no unconditional git reset --hard |
| Server-side build differs over time | Harder reproduction | Pin base/dependency inputs in service repos, record Git hashes/local image ids/build time |
| Migration blocks rollback | Extended outage | Expand/contract, measured locks, fresh backup, no automatic down migration |
| Redis loss drops queue/cache | Partial analytics interruption | AOF everysec, PostgreSQL authority, idempotent reconciliation/cold-cache tests |
| SSE buffering/timeouts | Dashboard appears stuck | Exact Nginx route, buffering/compression/cache off, heartbeat/reconnect test |
| Docker-group compromise | Host-root compromise | Restricted key-only access to trusted ubuntu account, no daemon TCP exposure |
| Backup leaks credentials | Wider compromise | Remove .env backup/restore, encrypt, separate passphrase, archive exclusion tests |
| Backup is unusable | Data loss beyond RTO | Checksums/listing/remote verification plus clean restore rehearsal |
| Delayed monitoring hides degradation | Slower MVP incident diagnosis | MVP health/log/operator checklist; mandatory Prometheus/Grafana before AI |
Parallelization after approval
- Safe in parallel: focused Nginx tests, backup adaptation, release-record validation, and later dashboards after shared paths/contracts are fixed.
- Sequential: deployment, migration, production restore, DNS/TLS cutover, one-time import, and MVP-to-observability phase gate.
- Cross-repository coordination: backend commands/health and frontend build/font behavior are defined by their owners before deployment consumes them; no automated pipeline is introduced.
Completion
- Every authorized task in
tasks/todo.mdpasses its acceptance and verification. - The active stack maps to exact deployment/backend/frontend commits.
- Rollback, Redis-loss recovery, backup, restore, import separation, and exposure checks pass.
- Prometheus/Grafana acceptance passes before AI begins.
- Deployment Git contains no application source, secrets, raw data, credentials, certificates, backups, volumes, or duplicate font/license assets.