Platform Operations implementation tasks
- Status: Ready for stakeholder review — implementation not authorized
- Canonical plan:
tasks/plan.md
Task 0: Resolve implementation inputs and preserve the implementation gate
Description: Use the approved manual Qlockify-style specification to collect the concrete values and service contracts required for later implementation while preserving the separate explicit build-authorization gate.
Acceptance criteria:
- Revised Platform Operations spec is explicitly approved.
- ADRs 0001–0003 match the approved topology, manual release, and font decisions.
- Production connection values, protected secrets, repository URLs, service commands/routes, and responsible operators are recorded outside public Git where required.
- Stakeholder explicitly authorizes creation of deployment implementation artifacts.
Verification: Approved specification, clean documentation review, resolved slice inputs, and explicit build authorization.
Dependencies: None
Files likely touched: spec and ADRs only
Estimated scope: Small
Task 1: Define safe configuration and release records
Description: Define tracked placeholders, external protected secrets, deployment locking, and non-secret active/previous release records.
Acceptance criteria:
- Release record contains three SHAs, local image ids, migration, backup, operator, and health evidence.
- Configuration examples contain no real or plausible secret values.
- Font provenance uses frontend commit/build only; no second asset path exists.
Verification: Schema/format tests, secret scan, invalid-record tests.
Dependencies: Task 0
Files likely touched: examples/schema/tests/docs, maximum 5 files
Estimated scope: Medium
Task 2: Implement PostgreSQL and Redis Compose foundation
Description: Add pinned PostgreSQL 18 and Redis 7 Alpine, private data network, volumes, authentication, health, resources, and approved Redis AOF choice.
Acceptance criteria:
- Both services become healthy with explicit limits/tags.
- Neither publishes a host port.
- Redis is excluded from backup and loss does not affect PostgreSQL authority.
Verification: Compose validation, health, port/network, volume, Redis-loss tests.
Dependencies: Task 1
Files likely touched: Compose/config/tests, maximum 5 files
Estimated scope: Medium
Task 3: Implement backend, worker, and one-off boundaries
Description: Wire API/worker plus separate migration/import/admin commands and graceful lifecycle.
Acceptance criteria:
- Migration completes before API/worker readiness.
- Normal startup never runs import/admin; import uses one exact read-only path.
first-start.shstarts data services, migrates, imports and reconciles the pinned archive, then starts public services only after success.- Worker is private/event-driven and uses pinned pre-1.0 Asynq
v0.26.0.
Verification: First-start, ordinary-startup, migration/import failure, checksum/count reconciliation, idempotent no-op, and shutdown integration tests.
Dependencies: Task 2 and approved backend commands
Files likely touched: Compose/service wrappers/tests, maximum 5 files per slice
Estimated scope: Medium
Task 4: Implement frontend build and font health
Description: Build the nested frontend checkout normally and verify static SPA/font output without deployment copies or injection.
Acceptance criteria:
- Build uses recorded frontend commit at/after
64f5ac2. - Expected font resource returns 200 with correct content type.
- Deployment repository contains no font binary,
FontLicense.txt, fetch, credential, or alternate path.
Verification: Build/static health plus repository-policy scan.
Dependencies: Task 1 and approved frontend build contract
Files likely touched: frontend deployment wrapper/service/tests, maximum 5 files
Estimated scope: Medium
Task 5: Implement Nginx and automatic TLS
Description: Adapt Qlockify's Nginx/Certbot pattern for canonical routing, Let's Encrypt, API/frontend separation, exact SSE behavior, security headers, and health.
Acceptance criteria:
- Only 80/443 are public; unknown hosts reject and canonical redirect is exact.
- Staging/production issuance and renewal/reload pass.
- SSE heartbeat/reconnect streams without buffering/cache/compression.
Verification: nginx -t, external TLS/header/routing checks, streamed SSE test.
Dependencies: Tasks 3–4 and approved routes/CSP
Files likely touched: Nginx/Certbot assets/tests, maximum 5 files per slice
Estimated scope: Medium
Checkpoint A: Runtime MVP foundation
- Tasks 1–5 pass from clean nested checkouts.
- Only Nginx is public; migration/import/admin/font/SSE boundaries behave correctly.
- No secret/raw data/runtime/font duplication enters deployment Git.
Task 6: Adapt Qlockify manual deploy and rollback
Description: Modify Qlockify's deploy flow for ZarinPal paths/services and three-hash release records while keeping interactive Git pulls as a separate operator prerequisite and removing unconditional destructive Git synchronization.
Acceptance criteria:
- Operator manually fast-forwards all three repositories to latest
origin/main; the deployment command performs no pull and records all three hashes before build. - Dirty/diverged checkout, build, migration, or health failure preserves the active release; a manual pull failure prevents deployment from starting.
- Previous hashes rebuild/restore within 15 minutes without automatic down migration.
Verification: Script tests plus induced staging failures and timed rollback drill.
Dependencies: Checkpoint A
Files likely touched: deploy script/release helper/tests/docs, maximum 5 files per slice
Estimated scope: Medium
Task 7: Adapt Qlockify encrypted backup/upload
Description: Reuse Qlockify's PostgreSQL dump, OpenSSL, rclone upload, and retention flow with ZarinPal paths/services/credentials and a non-secret manifest.
Acceptance criteria:
- Package contents, plain-SQL header/checksums, encryption, and remote verification gate success.
- Exactly three verified encrypted local and seven remote backups are retained.
.env, secrets, Redis, TLS, CSV, credentials, logs, monitoring, font, and license are excluded.
Verification: Fixture database/object-store tests, exclusion inspection, failed-upload/cleanup tests.
Dependencies: Tasks 1–3 and approved backup inputs
Files likely touched: adapted backup/upload scripts/tests/docs, maximum 5 files per slice
Estimated scope: Medium
Task 8: Adapt Qlockify guarded restore
Description: Reuse Qlockify download/decrypt/restore flow while requiring explicit backup id, exact destination, empty target, and all production guards.
Acceptance criteria:
- Every absent/mismatched production factor aborts before mutation.
- No environment/secret/Redis restoration occurs.
- Clean restore passes schema/count/tenant/login/cold-cache/worker/SSE checks within two hours.
Verification: Disposable-database tests, guard negative matrix, timed rehearsal.
Dependencies: Task 7
Files likely touched: adapted restore scripts/tests/docs, maximum 5 files per slice
Estimated scope: Medium
Task 9: Bootstrap and accept MVP server
Description: Follow the reviewed bootstrap runbook, run the guarded first-start migration/import/application sequence, perform separate demo setup, and capture MVP evidence.
Acceptance criteria:
- Access/firewall/Docker/DNS/TLS/deployment boundaries pass.
- Three-hash release, migration, import, accounts, tenant isolation, worker/SSE, and font pass.
- MVP manual health/log/disk/certificate/queue checks and encrypted backup/restore pass.
Verification: Completed bootstrap/acceptance record.
Dependencies: Tasks 6–8 and approved server/window
Files likely touched: non-sensitive release/evidence records only
Estimated scope: Operational session
Checkpoint B: MVP ready
- Every MVP acceptance criterion passes.
- Active/previous three-hash releases and rollback are ready.
- Clean restore meets RPO/RTO.
- Stakeholder explicitly confirms the core project is ready, opening the observability phase.
Task 10: Add Prometheus and private exporters
Description: Add post-MVP collection for application, worker/SSE, PostgreSQL/Redis, host/container, backup/restore, and TLS signals.
Acceptance criteria:
- Required signals appear with bounded labels and retention.
- Prometheus/exporters are private and resource-limited.
- Merchant/user/request/card identifiers are absent from metric labels.
Verification: Target health, signal/cardinality/resource tests.
Dependencies: Checkpoint B
Files likely touched: split into <=5-file monitoring slices
Estimated scope: Multiple Medium slices
Task 11: Add Grafana dashboards and alerts
Description: Add private dashboards, release correlation, actionable symptom alerts, runbook links, and delivery testing.
Acceptance criteria:
- Service, worker/SSE, data, host, backup, and TLS dashboards answer the spec's operator questions.
- Only page/ticket alerts exist and each is actionable.
- Induced failures alert and can be diagnosed without source archaeology.
Verification: Dashboard review, induced failure, alert test-fire, redaction check.
Dependencies: Task 10
Files likely touched: split into <=5-file dashboard/alert slices
Estimated scope: Multiple Medium slices
Final observability checkpoint before AI
- Prometheus/Grafana phase meets its acceptance criteria.
- Alert delivery and runbook ownership are proven.
- Stakeholder explicitly approves beginning AI implementation.
- No CI/CD pipeline or automated deployment system was introduced.